Stonewater Equipment Efficiency

In August of 2008 Neville took over management of three Class A office structures totaling 140,000sf. These structures were housed on the top of Water Tower Hill in Colchester, VT. One issue we faced related to the elevation of the structures and providing potable water to upper floors. The original owner had addressed the issue using jockey pumps. Continue reading

Capital Improvement Coordination

In September 2011, one of our institutional clients released substantial funding for capital projects with the requirement that work be completed by the end of the year. The projects included roof and asphalt replacement at several at several locations; with each project requiring a detailed scope of work and competitive bid. Continue reading

Accounting Perfection

Neville’s management team provides accounting services to individual, corporate and institutional portfolios; with institutional accounting requirements by far the most stringent. Continue reading